Shell Canada has delayed plans to ramp up capacity at its Corunna refinery.

Late last year, the company had reached the select phase of a project to expand from 80,000 barrels per day to 95,000.

Spokesman Randy Provencal says a number of factors went into the decision including the economic situation in Canada and the need to complete other projects.

[audio mp3="http://blackburnnews.com/wp-content/uploads/2015/08/Randy-2.mp3"][/audio]

Provencal says Shell is in a good position to move forward with expansion in Corunna at a later date.

The project would have seen the demolition of an old refinery unit and construction of a new one.

It would have created some 120 construction jobs and an undetermined amount of full time work.